Summer Construction Projects 2025

Summer renovation window is between 6/2-8/8

Hinsdale Central

Phase 3 of window replacement on building (Starting 6/2)
Department offices refresh: Social Studies, Business, FACS, Bookstore
New drywall ceilings in bathrooms (Starting 6/16)
Auditorium lobby refresh (Starting 6/23)
New gymnasium lighting (Starting 7/21)

Sealcoat/Stripe - Area of the parking lot will be intermittently unavailable due to construction work
Staff parking lot starting
(6/2-6/25)
Student parking lot (6/2-6/25)
Dickinson Field (Starting 6/2)
Bus dropoff lane (Starting 6/2)
Fire lane (Starting 6/2)

Repaving
55th Street entrance by Door #1 (6/2-6/25)
Near Door #3 and new concrete aprons (6/2-6/25)

Tuckpointing
Tuckpointing of brick facade starting (Starting 6/2)

Hinsdale South

Renovation of pool deck (4/14 -8/8)
Renovation of restrooms throughout building (Starting 6/2)
First and third floor hallway flooring replacement (Starting 6/2)
New Mother’s Room (Starting 6/2)
Athletics Office Refresh (Starting 6/2)
New gymnasium lighting (Starting 6/30)

Repaving
Repaving of North staff lot (Starting 6/2)
Repaving of West Stadium sports entrance (Starting 6/2)

Sealcoat/Stripe
West student lot (Starting 6/2)
Main entrance Door #1 (Starting 6/2)

Tuckpointing
Brick facade (Starting 6/23)

Village of Hinsdale
Repaving of Grant Street by Village of Hinsdale (6/8-6/30)